MINISTRY OF URBAN & REGIONAL PLANNING CHECKLIST
PROCESS & STEPS
MINISTRY OF URBAN AND REGIONAL PLANNING
BUILDING PLAN APPROVAL CHECKLIST
STEP 1: Assessment >>>
1 DAY
Acceptance for Assessment (Plan Okay for Registration)
STEP 2: Inspection/Registration >>>
1 DAY
Site Inspection and Registration
STEP 3: Charting/Vetting>>>
1 DAY
Charting / Vetting of Drawings
STEP 4: Recommendation >>>
2 DAYS
Vetting and Recommendation
STEP 5: Confirmation >>>
3 DAYS
Stamp and Seal / Receipt Confirmation
STEP 6: Approval >>>
2 DAYS
Building Plan Approval
STEP 7: Release >>>
1 DAY
Release of Building Plan